2009 Kaohsiung: Construction Update
31 Mar 2008 09:37
 

© KOC

The World Games Stadium is taking shape: the 55,000-capacity stadium has its metal roofing structure up already. Mayor Chen Chu led the ceremonies when the final beam was put in place on 28 March.

Construction on the imposing venue started on 28 December 2006. Exactly fifteen months later, over 60% of the work is completed, and the remaining part can easily be carried out over the next nine months.

The stadium, which covers 19 hectares, will cost US$150.6 million.

The stadium will be the world's first multi-functional stadium powered by solar energy. Its solar generators will supply 1 million kilowatts of electricity a year.


News of The World Games
2009 Kaohsiung: Court Ready
2009 Kaohsiung: Venue Names
The World Games 2009: Korfball With Shot Clock
Duisburg + Duesseldorf: Ratified
The World Games 2013: Duisburg + Duesseldorf
2009 Kaohsiung: Changes Within KOC
Sport Business: The Love of The Games
2009 Kaohsiung: Without Indoor Hockey
2009 Kaohsiung: Construction Update
IWGA President: Speaks Up On 2013
2009 Kaohsiung: Swiss Timing
The World Games 2013: Duisburg & Duesseldorf
2009 Kaohsiung: Free Your Desire 2
2009 Kaohsiung: Setting Sails
2009 Kaohsiung: Free Your Desire!
 
IWGA Headquarters
10 Lake Circle
Colorado Springs, CO 80906
USA
TEL: +1 719 471 8096
FAX: +1 719 471 8105
E-MAIL: info@worldgames-iwga.org
IWGA Communications
P.O. Box 110
17487 Empuriabrava
SPAIN
TEL: +34 972 45 60 02
E-MAIL: com@worldgames-iwga.org
 
© 2008 International World Games Association. All Rights Reserved. powered by sportcentric